At a recent seminar hosted by SIGMA, EPA officials indicated that transfer documentation would be satisfactory if initiated by the transferee as long as both parties agreed to this system. Please confirm this understanding?

Your understanding is correct. However, while EPA would not object to a cooperative agreement between the transferor and the transferee, the transferor remains liable if the transferee does not have all the required PTD information for each batch.(9/26/94)

This question and answer is posted at http://www.epa.gov/otaq/regs/fuels/rfg/qa/420r03009.pdf. The original was posted in the Q&A posted on 9/26/94 which can found at http://www.epa.gov/otaq/rfg_qa.htm" See Question ID 3857 for RFG (Taken from the first question on http://www.epa.gov/otaq/regs/fuels/rfg/qa/420r03009.pdf)